FDOT Standard Plans · FY 2026-27 · Series 125: Clearing Construction Site

FDOT Standard Plans Index 125-001: Utility Adjustments Thru Existing Pavement

Short answer

Index 125-001 is the FDOT Standard Plan for Utility Adjustments Thru Existing Pavement, part of Series 125 (Clearing Construction Site). The sections below are extracted from FDOT's Standard Plans Instructions (SPI) for this index — design criteria, assumptions and limitations, and what your plans must show.

Design Assumptions and Limitations

Design Assumptions and Limitations Index 125-001 provides the minimum requirements for the excavation and backfill of utilities placed below existing pavement on the State Highway System, including requirements for replacement of the pavement. Index 125-001 is intended to be used by Maintenance and utility permit operations. Department owned utilities (i.e., conduit and drainage pipe) placed during construction are to be installed and paid for in accordance with their respective Standard Plans and Specifications .

Payment

Payment No separate payment is made for the utility adjustments thru existing pavement.

pavementfillflowablestageutilityreplacementcoursebackfillengineerexistingbelowbase

How PDFDepth uses this index

When a plan set cites Index 125-001, PDFDepth's AI Plan Review cross-references the set against the Plan Content Requirements for the FDOT indexes it cites and flags items that appear to be missing — each with a citation to the sheet. A human reviewer verifies every flag before it counts.

Related indexes in Series 125

All FDOT Standard Plans indexes

Try it yourself — open your plan set in PDFDepth

Review, measure, and check plan sets against the standards they cite — free for 14 days.

Start for Free

Text extracted from FDOT Standard Plans FY 2026-27, a public-domain Florida state publication. Always verify against the current edition at fdot.gov. PDFDepth is not affiliated with FDOT.