FDOT Standard Plans Index 700-091: Catwalk Details (for DMS Signs)

Short answer

Index 700-091 is the FDOT Standard Plan for Catwalk Details (for DMS Signs), part of Series 700 (Signing, Pavement Markings and Lighting). The sections below are extracted from FDOT's Standard Plans Instructions (SPI) for this index — design criteria, assumptions and limitations, and what your plans must show.

Design Criteria

Design Criteria LRFD Specifications for Structural Supports for Highways Signs, Luminaires, and Traffic Signals ; Structures Manual (SM) , Volume 3

Design Assumptions and Limitations

Design Assumptions and Limitations For use with overhead DMS signs Index 700-090 . Assumed loading is an unfactored Live Load on the walkway of 60 psf with a maximum five-foot span. All walkways must have a 3” minimum height toe kick on the longitudinal edges that will support a 50- pound horizontal load.

Guiderails are designed to support a 200-pound point load and a 50 plf load simultaneously applied in a horizontal and vertical directions. Base spacing of the supports and the elevation of the walkway/bottom on the DMS sign support.

Payment

Payment There is no separate payment for the DMS Catwalk. See Specification Section 700 for additional information on payment, pay item use, and compensation.

What your plans must show

Plan Content Requirements for this index — the SPI's checklist for designers.

  • In the Structures and/or Roadway Plans: Include the truss chord spacing, distance from the bottom chord to the support beams the catwalk length, and number of supports required. Length of catwalk is dependent on accessibility by a bucket truck at the site. As a minimum, extend the catwalk over inside edge of shoulder. Coordinate with the District Traffic Operations and District Maintenance to confirm proper access is available. Consideration for Approval of Alternative Technical Proposals Alternate catwalk systems may be considered for approval with concurrence from the District Structures Design Engineer. Fabricators must be listed in the Material Acceptance and Certification System ( MAC ) as an approved Metals Production Facility. Design calculations meeting the wind load and live load requirements for the project site in accordance with the Structures Design Guidelines ( SDG ) , and minimum OSHA requirements must be submitted for review and approval by the EOR. Technical Specifications with material and testing requirements should be submitted by the Contractor for approval prior to acceptance of any alternative technical proposal ( Contractor Savings Initiative for Design-Bid-Build projects, or Alternative Technical Concept for Design Build/P3 projects).
generalsignguideraildetailsgratinghangerbeamcatwalkwalkwaysupportrevisioncantilever

How PDFDepth uses this index

When a plan set cites Index 700-091, PDFDepth's AI Plan Review cross-references the set against the Plan Content Requirements for the FDOT indexes it cites and flags items that appear to be missing — each with a citation to the sheet. A human reviewer verifies every flag before it counts.

Related indexes in Series 700

All FDOT Standard Plans indexes

Try it yourself — open your plan set in PDFDepth

Review, measure, and check plan sets against the standards they cite — free for 14 days.

Start for Free

Text extracted from FDOT Standard Plans FY 2026-27, a public-domain Florida state publication. Always verify against the current edition at fdot.gov. PDFDepth is not affiliated with FDOT.